Project Milestones
| Dec 2003 | Complete Site Inventory/Selection | Completed |
| Jan 2004 | Finalize Quality Assurance Management Plan | Submitted for Review |
| Jan 2004 | Submit Request for Qualifications | Submitted for Review |
| Jul 2004 | Complete Community Outreach | In Progress |
| Jul 2004 | Complete Phase I Assessments | Not Started |
| Jul 2004 | Complete Phase II Assessments | Not Started |
| Nov 2004 | Project Closeout | Not Started |
|
 |
|
|